|
Important: Due to the behaviors described below, you should not use effort-driven tasks as "maintenance task." Maintenance tasks are tasks of long duration usually with large numbers of assignees. To create maintenance tasks use non-effort-driven tasks.
In effort-driven tasks, the amount of work remains constant for a task. The duration of the task shrinks or grows as resources are assigned or removed from the task. The amount of effort (work) remains unchanged.
As members are added and removed, planned work remains the same.
Example: An effort-driven project task has 16 hours of planned work and one assignee. With an 8-hour workday specified in the workweek calendar, it will take the assignee 2 days to complete the task, creating a task duration of two days. When the project manager assigns a second team member to the task, the task duration changes to 1 day, as 2 people can complete the work in half the time.
With fixed-duration, effort-driven tasks, the resource allocation units change as team members are assigned or removed from the task. For examples, see Assignments and Fixed Duration - Effort Driven Tasks.
When a task is not effort-driven, assigning an additional team member to the task increases the task's planned work. For example, a project task has 16 hours of planned work, one assignee, and a duration of two days. When the project manager assigns a second team member to the task, planned work increases to 32 hours, and the task duration remains at 2 days.
Note: The duration of an effort-driven task only changes when the number of team members assigned to the task changes.
Related Topics: