Actual Cost (task field)

Derived - The Actual Cost of a task is calculated by multiplying the actual work by the hourly rate(s) of task assignees.

Actual Cost = (Actual Work x Hourly Rate(s))

Note:For enterprises using Timesheets, a timesheet must be submitted (and approved, if applicable) before work becomes Actual Work.

 