Microsoft Project includes several task constraint types that are not supported in Changepoint PPM (As Late As Possible, Finish No Earlier Than, Finish No Later Than, Start No Earlier Than, Start No Later Than).
To handle this difference, ProjectTransit maps PPM task constraints to Microsoft Project constraints in the following ways.
PPM Constraint Type | Microsoft Project Constraint Type |
---|---|
|
|
|
|
|
|
|
|
Microsoft Project Constraint Type | PPM Constraint Type |
---|---|
|
|
|
|
|
|
|
|