About Task Constraints in ProjectTransit

 

Microsoft Project includes several task constraint types that are not supported in Changepoint PPM (As Late As Possible, Finish No Earlier Than, Finish No Later Than, Start No Earlier Than, Start No Later Than).

To handle this difference, ProjectTransit maps PPM task constraints to Microsoft Project constraints in the following ways.

Mapping Changepoint PPM Tasks to Microsoft Project Tasks:

PPM Constraint Type Microsoft Project Constraint Type
  • As Soon As Possible
    (PPM Default constraint type)
  • As Soon As Possible (ASAP)
  • Must Start On
  • Must Start On (MSO)
  • Must Finish On
  • Must Finish On (MFO)
  • None
  • Start No Earlier Than <date>
    (<date> = PPM task Planned Start Date)

 

Mapping Project Tasks to PPM Tasks:

Microsoft Project Constraint Type PPM Constraint Type
  • As Soon As Possible (ASAP)
  • As Soon As Possible
  • Must Start On (MSO)
  • Must Start On
  • Must Finish On (MFO)
  • Must Finish On
  • all other constraint types
  • None

 

 