About Task Properties

 

The interaction between various task attributes (type and assignees) and properties (planned work, duration and resource allocation units) control what happens in a project schedule. Understanding these interactions is important for project managers and others who are responsible for creating and/or maintaining a schedule.

Attributes

 

Properties

These three properties interact, based on task type and assignees.

 

How task properties are calculated

When you change a task property, the other properties are recalculated using the equation:

Planned Work = Duration x Units

where:

 

Related Topics: