Adding a Task Using the Create Task Window
|
Note: For information on adding tasks directly from the Task List, see Adding a Task in the Task List.
When you add a task, you provide a name and description, as well as information such as the intended
start and finish dates (Planned Start and Planned Finish). You can also assign the task to team members if
you are ready to do so. Any assigned team member will receive
a notification that the task has been created and assigned to them.
Default Task Type
By default, the task type is Fixed Duration (non effort driven). Any task you create in PPM defaults to this type, unless you change the type. If you change the task type, the change persists until you change it again. This means that any place you create a task will use the values you last set until you change them again. The task type default is a default only for the logged in user. Another user in the same project may have a different default task type.
To add a task:
- On the , click Create Task.
The Create New Task window opens.
- Select a Workspace for which you are adding the task.
The list includes all workspaces you are member of and defaults to the workspace you selected the last time you created a task in the Create New Task window.
- Type a Task
Namefor the task.
- To provide more detail about the task, include a Description.
The description might include information about why the task is being
created.
- Type or select the Planned
Start date on which you intend for the task to start.
- Type or select the Planned
Finish date on which you intend for the task to end. By default
Planned Finish is set to the same date as Planned Start.
Note: If you clear the Planned Finish box, the date is automatically
generated based on the duration you type for the task Duration.
- In the Duration
box, type the number of days the task will last.
By default the duration is set to the number of days from the planned
start date and the planned finish date. If you change the duration, the
planned finish date will automatically adjust for the correct number of
days.
- In the Planned
Work box, type the number of hours the task will take to complete.
- From the Priority
list, select Low, Medium,
or High to set the priority of the task.
- Specify task properties (milestone, deliverable, or billable) in the Task Properties section.
(
Show me more)- Milestone—A
is a task that identifies a key event in the schedule.
- Deliverable—A deliverable
is something produced during project execution. If the task is a deliverable
component of the project, select Deliverable.
- Billable—A billable
task is assumed to be billed externally and includes fields for that billing.
A non-billable task has its external rate field disabled.
For more information, see About
Billable and Non-Billable Tasks.
Note:The Billable option is hidden if external billing is not enabled for the workspace.
- To assign team members
to the task,click Browse Member Directory
and choose team members to whom you are assigning the task.
Note: For details about how to use the Member Directory, see
Using the User Selector.
- Specify advanced task information
(task type, constraint information, and task number) in the Advanced
Information section.
(Show me more)- Task
Type—Task
type defines which task property remains fixed. Select from Fixed Units,
Fixed Duration, or Fixed
Work. For details on task types, see Task
Type Overview.
Note: If you change the task type, the new setting persists
until you change it again. This setting applies whenever you add a task
in PPM, including when adding tasks using the Task List. For more information,
see Adding a Task in the Task List. - Effort
Driven—If
the duration of the task should be updated when the number of assigned
team members changes, select Effort Driven.
- Insert
After Task#—Select
the position in the task list where the new task will be inserted.
Options are Top, or the number
of any existing task. - Constraint
Type—Select
an option to specify whether or not there is a constraint on the dates
of the task.
Options include, None, Must Start On, Must
Finish On, and As Soon As Possible(the default).
For more information, see Task
Constraints Overview. - Constraint
Date—If
the constraint type is either Must Start
On or Must Finish On, type
a date in the Constraint Date
text box, or click on the calendar icon and select a date from the calendar.
- Task
External Rate—To
specify a task-level external billing rate for a billable task, type the
rate value in the External Rate
box, or click the Billing Rate Selector icon
and select
a predefined rate.
Note: You can only set an external billing rate if the task
is billable and the workspace has external billing enabled. For more information
see About Billable
and Non-Billable Tasks.
Any external rate entered here is used only for work done on this task
and overrides any external rate set at other levels (the workspace member
or enterprise resource level for example). If you do not specify a task-level
external rate on a billable task, the rate defaults to the external rate
of the workspace member assigned to the task. If there is more than one
assignee and you do not specify a task-level rate, the rate is determined
by the external rates of the assignees and the amount of work each does
on the task.
- If another task must be
started or finished before this task can begin, specify the details for
the predecessor in the Select Predecessors
section.
(
Show me more)- Select
Predecessor Task from—From
the list of existing tasks, select the task that is the predecessor of
the task you are creating.
- Dependency
Type—Select
the type of dependency that represents the dependency the new task has
with its predecessor task. Options are:
- Finish to Start—The
predecessor task must finish before the new task can start.
- Start to Start—The
predecessor task must start before the new task can start.
- Finish to Finish—The
predecessor task must finish before the new task can finish.
- Lag—Type the number
of days delay between predecessor and successor tasks. To enter lead time,
type a negative number. For more information about lag and lead time,
see About Lag and Lead Time.
- Add—Click Add to add the predecessor task to the
Selected Predecessors list.
- To add a cross-project
predecessor, in the Select Cross-Project
Predecessors section.
(
Show me more)- Select Predecessor Tasks from—Select the
project which contains the predecessor task.
- Select
Predecessor Task Below—From
the list of existing tasks, select the task that is the predecessor of
the task you are creating.
- Dependency
Type—Select
the type of dependency that represents the dependency the new task has
with its predecessor task. Options are:
- Finish to Start—The
predecessor task must finish before the new task can start.
- Start to Start—The
predecessor task must start before the new task can start.
- Finish to Finish—The
predecessor task must finish before the new task can finish.
- Add—Click Add to add the predecessor task to the
Selected Predecessors list.
- In the Notifications
section, select the team members who can view the task, and team
members who should be notified that the task has been created. Note: Assignees get an automatic notification about the task. You only need to specify assignees here if you are including something in your custom notification message that they need to see.
Click Browse Member Directory
to select team members.
- To include a custom message
in the notification, select Type Custom
Notification Message.
A Notification Message box
displays. Type the message to be sent to team members who are notified
of the Issue.
- Click Save
& Close to save the new task and close the Create New Task
window, or Save & Add Another
to save the new task and leave
the window open so you can add another task.
Note: If global or personal nonworking time affects the assignee, Planned Finish is automatically adjusted when you add an assignee or change a duration. A changed field indicator displays in the Pl. Finish column of the Task List when this occurs.
Related Topics: