Adding a Task in the Gantt Chart
|
Project managers can add tasks directly into the Gantt Chart. For information
about other ways to add tasks in PPM, see Adding
a Task.
You must check out the task schedule in order to add, edit,
and delete tasks in the Gantt Chart. For more information about checking
the schedule out, see Checking
Out the Task Schedule for Editing.
TO add A TASK IN THE GANTT CHART:
- to which you want to add the summary task.
You need to check the schedule out before you can add a summary task.
- Click Tasks
in the Workspace Menu, then click Check
Out Schedule.
If the task schedule is already checked out, a Check
In Schedule link displays on the Tasks menu, and a Check
In button displays at the top of the List and Outline views. For
more information, see Checking
Out the Task Schedule for Editing.
- In the Tasks
area of the Workspace Menu, click Gantt Chart.
The Gantt Chart displays in a new window.
- Do one of the following
in the Task list to the left of the Gantt chart:
- Click an empty
row
- Click the Task
number of an existing Task, and then click Insert (
) on the Gantt
Chart toolbar.
A new task is added above the existing task.
- Type a name for the task
in the Task column and then press
Enter. The task is added to the
Gantt chart with a default duration of 1 day.
- To specify a different
task duration, type a number in the Duration
text box.
Note: A duration of 0 creates a .
- To specify task start and
end dates, do one of the following:
- In the task details
section at the top of the
Gantt chart, type dates in Start
and Finish, or double-click
in the boxes and select dates from the pop-up calendar.
- In the Gantt chart,
drag the task bar to a new position in the schedule.
- To specify the percentage
of the task that is complete, in the task details section above the Gantt
chart, type a number in the % Complete
text box. Note: if your organization uses
ETC to track task progress the % Complete field is not editable.
- To assign a resource to
the task, in the task details section at the top of the Gantt chart, double-click
the Resource text box.
Select a resource from the pop-up list of team members. For more information,
see Assigning
Team Members to Tasks.
- To save changes made in
the task details section, press Enter.
- To specify additional details
about the task, such as the task type, constraints, and whether the task
is effort-driven, click the Edit Task
Details button on the Gantt Chart toolbar, and follow the procedure
Editing a Task in the Gantt Chart.
Note: The default task type is Fixed Duration (non-effort driven). If you have not changed this when adding a task in the Task List Add pane or the Create New Task window, this remains the default task type. If you change the type while adding a task, your change becomes the default task type until you change it again. For more information, see Task Types Overview.
- To add more tasks, repeat
this procedure from Step 4.
- To save your changes, close
the Gantt Chart and check
in the schedule.
Note: If a project
has been synchronized with a Microsoft Project file using ProjectTransit,
you cannot add, edit, or delete a task in PPM. For more information
about ProjectTransit, see ProjectTransit
Overview.