Moving a Task in the Gantt Chart
|
Drag tasks in the Gantt chart to new locations to move the tasks.
To Move a Task in the Gantt Chart:
- whose task you want to move.
Note: You need to check the schedule out before you move a task.
- Click Tasks in the Workspace Menu, then click Check Out Schedule.
If the task schedule is already checked out, a Check In Schedule link displays on the Tasks menu, and a Check In button displays at the top of the List and Outline views. For more information, see Checking Out the Task Schedule for Editing.
- In the Tasks area of the Workspace Menu, click Gantt Chart.
The Gantt chart displays in a new window.
- Click the number of the task you want to move and drag the task to a new location in the Task Grid.
Note: You cannot convert tasks into summary tasks if there is actual work logged against them.
Related
Topics: