Troubleshooting Tasks in the Gantt Chart
|
This topic is designed to help you troubleshoot problems
encountered when working with tasks in the Gantt Chart. Note: For troubleshooting tips when working with tasks in the project-level Task List, see Troubleshooting Tasks in the Task List.
Click a link below
for help with a specific problem:
Tasks are
not displayed in the Gantt Chart
- The view may have a filter applied to it.
The Gantt Chart view
can be filtered to limit the displayed tasks. Filters include All Tasks, Summary tasks, Milestones, Milestones & Summary tasks, Critical Tasks, Overdue tasks, and Unassigned tasks.
To show all
tasks, select All Task from the
Show list on the Gantt chart toolbar.

I cannot add or edit tasks
- You may not have
the schedule checked out.
To edit or add tasks in the Gantt chart, you
must check out the task schedule. For details on checking a task schedule
out, see Checking
Out the Task Schedule for Editing.
- The schedule may be checked out by another team member.
You cannot edit tasks in the Gantt chart when the schedule is checked out by someone other than you. When the task schedule is checked
out a message displays at the bottom of the Gantt chart.
- You may not have
permission to edit the task schedule.
To edit tasks in the Gantt chart, you need appropriate permissions. Contact your PPM administrator
to verify that you have adequate permissions.
- The task schedule
may be locked by ProjectTransit.
When a schedule is synchronized with Microsoft Project it is locked. Tasks cannot be added, edited,
or deleted in PPM until synchronization is turned off. For more information,
see Overriding ProjectTransit Schedule Synchronization.
Important: Turning off ProjectTransit synchronization is an irreversible step and should only be done if the schedule will not be used with ProjectTransit in the future.
I cannot indent or outdent tasks
- The task has logged against it.
Tasks with work logged cannot become summary tasks.
Note: This will not prevent you from indenting a task.
- You may be trying
to work with tasks that cannot be indented or outdented. The following
restrictions apply when working with summary tasks and sub-tasks:
- Top level tasks
cannot be outdented.
- The first task
in the task list cannot be indented.
I cannot delete or insert tasks
- The task may not be properly selected.
The task row must be highlighted when selecting a
task to delete or when selecting a task above which to insert a new task.
- To the left of the Gantt
chart, in the # column, click
the required task number. The task row is highlighted in the list:

- Click Delete (
) or Insert (
) on the Gantt chart toolbar.
- The selected task may have actual work logged against it.
Tasks with work logged against them cannot be deleted.
Note: This will not prevent you from inserting tasks.
I cannot change task dates or move tasks
- There may be constraints
on the task.
A constraint is a restriction on the task start or finish
date. If a task has a constraint, you may not be able to change its start or finish date.
To remove a constraint, double-click the task in the Gantt chart, click
the Advanced tab, and then select
None from the Constraint
Type list. For more information, see Task
Constraints.
- There may be restrictions
on the task start/finish dates. Tasks that are linked to other tasks with
a dependency may have restrictions on their start and finish dates.
For example, if a finish to start dependency links two tasks, the start
date of the successor task must be after the finish date of the predecessor
task. Linked tasks are joined with an arrow in the Gantt chart. Double-click
the arrow to view details of the link between the tasks. For more information,
see Task Dependencies.
Tasks have moved in the task schedule
- The task may be linked to other tasks.
Tasks that are linked
by dependencies to other tasks may move when linked tasks are moved.
For example, if a finish to start dependency links two tasks, changing
the finish date of the predecessor task automatically changes the start
date of the successor task.
Linked tasks are
connected with an arrow in the Gantt chart. Double-click the arrow to view
details of the link between the tasks. For more information, see Task
Dependencies.
Task durations do not match the task bars
in the Gantt chart
- The task may span non-working days.
Some days are marked
as non-working days in the workweek calendar. Typical examples of non-working
days are weekends and public holidays. If a task includes non-working
days, the length of the task bar in the Gantt chart will appear longer
than the actual task duration.
For example, a task with a duration of 4 days that begins on Friday
will finish on the following Wednesday, as no work can be completed over
the weekend.
- The task duration may not be in complete days.
A task can have a
duration that includes part of a day, but task bars in the Gantt chart
are only displayed as full days.
For example, a task with 20 hours of planned work and one assignee
has a duration of 2 1/2 days, based on a 40 hour workweek calendar, but
the task would appear to have a duration of 3 days in the Gantt chart.
Task duration changes when I add or remove
task resources
- Tasks are effort-driven tasks.
Tasks that are marked as effort-driven have their duration
automatically updated when team members are assigned or removed from the
task. To remove effort-driven scheduling for a task, double-click the
task in the Gantt Chart, click the Advanced
tab, and then clear the Effort Driven
check box. For more information, see Effort-driven
Tasks.
Task properties (duration, planned work,
or resource allocation) are changing automatically
- When task properties are changed,
other properties change to reflect the impact on the schedule. The changes
made depend on the task type. For more information, see the Task Types Overview.
Team members are over-utilized
In the Gantt Chart, to view team member
utilization, open the Gantt Sidebar and click the Resource Utilization toggle
in the toolbar.
An icon
next to each resource name in the Sidebar indicates
how much of the resource's time is allocated to tasks.
Note: If the icons do not appear, select a task. The utilization display requires that a task be selected. Utilization is based on the time period of a particular task.
Team members that are over-utilized for
the duration of the selected task are marked with a warning icon
. Team members can become over-utilized
when they are assigned to more than one task at the same time.
For more information, see Viewing Resource Utilization.
To reduce the amount of work allocated
to a team member, you can remove the team member from some project tasks.
I cannot add a task to my timesheet
If you are trying to add a task to your timesheet and are a member of the workspace but cannot see the workspace to select a task, the workspace may not have a state that allows you to add one of its tasks.
- You can only add tasks to your timesheet if they belong to a workspace with a state of In Progress or Not Started. Tasks from workspaces with a state of Completed, Cancelled or On Holdcannot be added. For more information, see the About Tasks and Timesheets.
I cannot display critical path for my schedule
If you are trying to display critical path for a schedule and the Display Critical Path button is disabled, PPM is unable to calculate the critical path for the schedule. There are several reasons why this might be the case:
- The schedule includes a circular reference. Where this is the case, you can correct the dependency and PPM will be able to calculate the critical path.
For example, a task might have a Must Finish Before dependency on a task that has a Must Finish After dependency on the first task. The most common reason these types of problems exist is when a schedule has been imported from Microsoft Project or is synchronized with a Microsoft Project schedule using ProjectTransit.
- The schedule may be complicated, with numerous levels of indentation and dependencies. In this case, you may not be able to use PPM to calculate critical path.
Note: This should be a rare occurrence.
Related Topics: