Editing a Task in the Details Window
|
You can edit tasks from several locations in PPM. This topic addresses editing tasks from the global Tasks application. For other options, see Editing a Task.
Editing a task is not the same as updating a task. For more information about the differences, see Task Edit and Task Update.
Note: If a workspace
has been synchronized with a Microsoft Project file using ProjectTransit,
tasks cannot be added, edited, or deleted in the workspace in PPM.
For more information about ProjectTransit, see ProjectTransit
Overview.
To edit a task in the Details Window:
- In the , click the Actions
icon
next to the name of the task you want to edit, then
click Edit Task.
The Edit Task window opens.
- Type or edit the Task
Name.
- Type a Description of the task.
The description might include information about why the task is being
created.
- Type a Planned
Start or click
the pop-up calendar
to select the date on which the task starts.
- Type the Planned
Finish or
click the pop-up calendar
and select the date on which the task will end.
By default
the planned finish date is set to the same date as the planned start date.
Note: If you clear the Planned Finish box, the date is automatically
generated based on the duration you type in the Duration
box.
If you use ETC to and you change Planned Finish on a task that has no logged, ETC will be set to 0.
- In the Duration
box, type the number of days the task will last.
By default the duration is set to the number of days from the planned
start date and the planned finish date. If you change the duration, the
planned finish date will automatically adjust for the correct number of
days.
- In Planned
Work, type the number of hours the task will take to complete.
- Select Low, Medium,
or High to set the Priority of the task.
- Specify task properties (milestone, deliverable, or billable) in the Task Properties section.
(
Show me more)- Milestone—A
is a task that identifies a key even in the project schedule.
- Deliverable—A deliverable
is something produced during project execution. If the task is a deliverable
component of the project, select Deliverable.
- Billable—A billable
task is assumed to be billed externally and includes fields for that billing.
A non-billable task has its external rate field disabled.
For more information, see About
Billable and Non-Billable Tasks.
Note: If external billing is disabled for the workspace
the Billable option will not display.
- To assign team members
to the task, in the Select Assignees
section, click Browse Member Directory
to select team members to whom you are assigning the task.
Note: For details about how to use the Member Directory, see
Using the User Selector.
- Specify advanced task information
(task type, constraint information, and task number) in the Advanced
Information section.

(Show me more)- Task
Type—Task
type defines which task property remains fixed. Select from Fixed Units,
Fixed Duration, or Fixed
Work. For details on task types, see Task
Type Overview.
- Effort
Driven—If
the duration of the task should be updated when the number of assigned
team members changes, select Effort Driven.
- Insert
After Task#—Select
the position in the task list where the new task will be inserted.
Options are Top, or the number
of any existing task. - Constraint
Type—Select
an option to specify whether or not there is a constraint on the dates
of the task.
Options include, None, Must Start On, Must
Finish On, and As Soon As Possible.
For more information, see Task
Constraints Overview. - Constraint
Date—If
the constraint type is either Must Start
On or Must Finish On, type
a date in the Constraint Date
text box, or click on the calendar icon and select a date from the calendar.
- Task
External Rate—To
specify a task-level external billing rate for a billable task, type the
rate value in the External Rate
box, or click the Billing Rate Selector icon
and select
a predefined rate.
Note: You can only set an external billing rate if the task
is billable and the Workspace has external billing enabled. For more information
see About Billable
and Non-Billable Tasks.
Any external rate entered here is used only for work done on this task
and overrides any external rate set at other levels (the workspace member
or enterprise resource level for example). If you do not specify a task-level
external rate on a billable task, the rate defaults to the external rate
of the workspace member assigned to the task. If there is more than one
assignee and you do not specify a task-level rate, the rate is determined
by the external rates of the assignees and the amount of work each does
on the task.
- If another task must be
started or finished before this task can begin, specify the details for
the predecessor in the Select Predecessors
section.
(
Show me more)- Select
Predecessor Task from—From
the list of existing tasks, select the task that is the predecessor of
the task you are creating.
- Dependency
Type—Select
the type of dependency that represents the dependency the new task has
with its predecessor task. Options are:
- Finish to Start—The
predecessor task must finish before the new task can start.
- Start to Start—The
predecessor task must start before the new task can start.
- Finish to Finish—The
predecessor task must finish before the new task can finish.
- Lag—Type the number
of days delay between predecessor and successor tasks. To enter lead time,
type a negative number. For more information about lag and lead time,
see About Lag and Lead Time.
- Add—Click Add to add the predecessor task to the
Selected Predecessors list.
- To add a cross-project
predecessor, in the Select Cross-Project
Predecessors section.
(
Show me more)- Select Predecessor Tasks from—Select the
workspace which contains the predecessor task.
- Select
Predecessor Task Below—From
the list of existing tasks, select the task that is the predecessor of
the task you are creating.
- Dependency
Type—Select
the type of dependency that represents the dependency the new task has
with its predecessor task. Options are:
- Finish to Start—The
predecessor task must finish before the new task can start.
- Start to Start—The
predecessor task must start before the new task can start.
- Finish to Finish—The
predecessor task must finish before the new task can finish.
- Add—Click Add to add the predecessor task to the
Selected Predecessors list.
- In the Notifications
section, select the team members who can view the task, and team
members who should be notified that the task has been created.
Click Browse Member Directory
to select team members.
For details on selecting team members, see Using
the User Selector.
- To include a custom message
in the notification, select Type Custom
Notification Message.
A Notification Message box
displays. Type the custom message to be sent to team members who are notified
of the Issue.
- Click Save
& Close to save the new task and close the Create New Task
window, or Save & Add Another
to save the new task and leave
the window open so you can add another task.
The Edit Task window contains the same fields as the Create
Task window. For more information, see Adding
a Task. Click Save & Close to save
your changes and close the Edit Task window.
Note: If the edits you make
allow Global or Personal Nonworking Time to affect the assignee for the
task, the Planned Finish will automatically be adjusted when the task
is saved. You will be notified of the change when you save the task and
you can view the changes by going to the task history log, if task history
tracking is enabled, or in the save confirmation message if task history
tracking in not enabled.
Task Edit task edit
Related
Topics: